Production Lead Time, Inventory Days and the VSM Timeline

Beginner 7 min read · Updated 2026-10-31

The timeline (lead time ladder) is the result of value stream mapping at a glance: waiting times in inventory on top, processing times below. Their totals are the production lead time and the processing time; their ratio is the value-added ratio.

Inventory days calculator

–

Inventory days

Inventory is counted in pieces and converted into days using daily demand. 1,380 pieces at a demand of 920 pieces per day last 1.5 days. For the timeline, the inventory days are converted into seconds using the working time per day, so they can be compared with processing times.

Inventory days = inventory [pcs] ÷ customer demand per day [pcs]

Production lead time and processing time

Production lead time follows the main path of the material flow: the longest connected path from raw material to shipping. Side branches such as purchased parts count toward total inventory but not toward lead time. Processing time is the sum of the cycle times on this path.

If processing time is 2.6 minutes and production lead time is 11.3 working days of 920 minutes, a part spends 99.97% of its time waiting; the value-added ratio is 0.02%. This metric (internationally also called process cycle efficiency) is the most important number when you make the case to management. Always state the day basis: with calendar days instead of working days, the ratio drops further.

Production lead time = Σ inventory days + Σ cycle times Value-added ratio = processing time ÷ production lead time Flow factor (Erlach) = production lead time ÷ processing time

Levers to shorten lead time

Practice in the editor

In the demo, cut the "Finished goods" inventory in half and watch the timeline, lead time and value-added ratio.

Open the template in the editor Start blank

Free, no sign-up, in your browser. Metrics, timeline and checks are calculated automatically.

Frequently asked questions

Why does purchased-parts inventory not count toward lead time?

Purchased parts join a process from the side. Production lead time measures the longest path of the main material; purchased parts add to total inventory but not to the time of the main part.

Is a lead time of 10 days bad?

That depends on the processing time. With 3 minutes of processing, 10 working days of 8 hours give a value-added ratio of 0.06%, typical for push production with weekly scheduling. After a future-state design, 1 to 3 days is realistic.

Self-test

1. Inventory 2,000 pieces, demand 500 pieces per day: inventory days?
2,000 ÷ 500 = 4 days.
2. Which time is shown on the bottom of the timeline?
The bottom shows the cycle times of the processes, the top shows the inventory days.
3. Processing time 5 min, lead time 5 days of 8 h: value-added ratio?
5 min ÷ 2,400 min = 0.21%.