Takt Time Calculation: Formula, Example and Calculator

Beginner 6 min read · Updated 2026-10-31

Takt time is the heartbeat of the value stream: how many seconds can pass between two finished parts leaving the plant so that demand is met. Every future-state design is built around it.

Takt time calculator

–

Formula

Takt time is calculated from the available working time per day and the customer demand per day. Breaks and planned downtime are subtracted from working time; breakdowns are not.

Takt time [s] = available working time per day [s] ÷ customer demand per day [pcs]
Example: two 8-hour shifts with a 30-minute break each give 15 hours = 900 minutes = 54,000 seconds. With a demand of 920 pieces per day, takt time is 54,000 ÷ 920 = 58.7 seconds.

Takt time and cycle time

Takt time comes from the market. Cycle time is the actual output of a process, measured between two finished parts. If cycle time is above takt time, the process cannot meet demand; if it is well below, the process builds ahead.

The effective cycle time accounts for uptime, performance rate, scrap and changeovers: cycle time ÷ uptime ÷ performance rate ÷ (1 − scrap rate) + changeover time ÷ batch size. Uptime only covers breakdowns; changeovers are counted through changeover time and batch size, so nothing is deducted twice. Only the effective cycle time can be compared with takt time.

In German plants, "Taktzeit" and "Kundentakt" usually mean the same thing: takt time. What needs to be kept apart is the planned cycle time of a line. It is set slightly below takt time on purpose, so that small disruptions do not hit the customer right away.

Common mistakes

Practice in the editor

In the "Machine building" template, change the working time and customer demand and watch which processes slip above takt.

Open the template in the editor Start blank

Free, no sign-up, in your browser. Metrics, timeline and checks are calculated automatically.

Frequently asked questions

Is there a difference between takt time and customer takt?

Usually not: both mean the time per part set by customer demand (takt time). What is different is the planned cycle time of a line, which is set a little shorter than takt time so that disruptions do not hit the customer right away.

How do I calculate takt time with multiple shifts?

Add up all shifts and subtract breaks: for example, 3 shifts of 7.5 net hours = 22.5 hours = 81,000 seconds per day.

What if cycle time is above takt time?

Increase uptime (TPM), cut changeover time (SMED), redistribute work content (operator balance), or add a parallel station. ValueStreamMapping.app shows such processes in red and states the action needed.

Self-test

1. Available time 27,000 s, demand 450 pieces: what is the takt time?
27,000 ÷ 450 = 60 seconds.
2. Which time does not belong in the available working time?
Planned breaks are subtracted. Breakdowns are covered by the uptime, changeovers by the changeover time and batch size of the process, not by the working time.
3. Cycle time 50 s, uptime 80%, takt 60 s: can the process meet demand?
Effective cycle time 50 ÷ 0.8 = 62.5 s is above the takt of 60 s.