Milk Run and Mizusumashi: Supplying the Line on a Fixed Cycle

Advanced 7 min read · Updated 2026-10-31

In the future state the line no longer fetches its own material, and the forklift no longer drops off a whole day’s supply. A tugger train runs a fixed route on a fixed cycle: it brings material from the supermarket, takes empties and kanban cards back and often delivers the next heijunka card to the pacemaker. In the Toyota Production System the driver is called mizusumashi, a water strider insect, known in English as the water spider.

External and internal milk run

The term comes from the milk truck that visits fixed farms in a fixed order. Externally, a truck on a milk run picks up from several suppliers or delivers to several customers; on the value stream map it is a shipment with a frequency, such as “daily, milk run” at the customer in the steering bracket example.

Internally, the milk run is a tugger train route between supermarket and line. It replaces trips on request with a timetable: every stop is visited on every round, even if little is needed there at the moment. This makes material supply as predictable as production itself.

What the mizusumashi does

Route cycle time and utilization

The route cycle time is usually the pitch, the time in which one container quantity is consumed at takt time. A round consists of travel time and handling at each stop. It has to fit into the cycle time with a reserve, otherwise the next stop is served too late.

Pitch = takt time × pack-out quantity Utilization = (travel time + stops × handling time per stop) ÷ route cycle time
Steering bracket example (future state): takt time 60 s, pack-out quantity 20 pcs, pitch = 60 s × 20 = 1,200 s = 20 min. Every 20 min the tugger train serves three stops: stamped-parts supermarket, cell, heijunka box. Travel time 8 min, handling 2 min per stop: (8 + 3 × 2) ÷ 20 = 14 ÷ 20 = 70% utilization. The template “Steering bracket (future state)” includes this route.

How much utilization is right?

Plan for 70 to 85%. The reserve absorbs waiting at stops, breakdowns and occasional extra trips. Above 100% the driver cannot complete the round and the line waits. The fixes are fewer stops per route, shorter handling (containers within easy reach, cards in fixed slots) or a second tugger train.

Below 50% it pays to combine routes or give the mizusumashi other tasks, such as preparing changeovers. Do not simply lengthen the route cycle time for this: every extra minute of cycle time means more inventory at the line.

Line-side inventory and kanban

The point of use only needs enough material to last until the next round, plus a reserve. A card that is freed shortly after the stop waits until the next round and comes back filled one round later. Replenishment lead time through the tugger train is therefore up to two route cycles.

Demand per round = route cycle time ÷ takt time Line-side inventory ≈ 2 rounds × demand per round (+ safety)
Example: 1,200 s ÷ 60 s = 20 pcs per round, so about 40 pcs at the line instead of a full day’s 920 pcs dropped off once a day by forklift. The kanban formula with replenishment lead time is in the lesson /learn/kanban-supermarket-sizing/

In the editor

In Pro mode you find the symbol “Route train (mizusumashi)” in the palette under Material. Enter route cycle time, stops, travel time, handling per stop and containers per round. The symbol shows utilization, orange from 85% and red above 100%; the checks on the right report the same. Connect the supermarket to the route train with pull and the route train to the consumer with a delivery. Lead time and timeline do not change, because the route train sits alongside the material flow.

Practice in the editor

Open the template “Steering bracket (future state)”, switch to Pro mode and click the route train. Increase the stops to 5: at what number does the check report utilization that is too high?

Open the template in the editor Start blank

Free, no sign-up, in your browser. Metrics, timeline and checks are calculated automatically.

Frequently asked questions

What is a mizusumashi?

The driver of a tugger train in the Toyota Production System, literally a water strider, in English the water spider. The driver supplies the line from the supermarket on a fixed cycle, takes empties and kanban cards back and hands heijunka cards to the pacemaker.

What is the difference between a milk run and a tugger train?

Milk run describes the principle: fixed route, fixed cycle, several stops. Externally a truck runs it between suppliers or customers; internally a tugger train runs it between supermarket and line.

How long should the route cycle time be?

Usually as long as the pitch, 20 min in the steering bracket example. Shorter cycles reduce inventory at the line but increase the number of trips and therefore the driver’s utilization.

When do I need a second tugger train?

When utilization is above about 85% and handling or stops cannot be reduced further. Then split the stops across two routes instead of lengthening the route cycle time.

Self-test

1. Route cycle time 20 min, travel time 8 min, 3 stops with 2 min handling each. What is the utilization?
(8 + 3 × 2) ÷ 20 = 14 ÷ 20 = 70%.
2. Takt time 60 s, pack-out quantity 20 pcs. What is the pitch?
60 s × 20 = 1,200 s = 20 min.
3. Utilization is 105%. What is the best first action?
A longer cycle time or more inventory hides the problem and increases inventory. Fewer stops per route or shorter handling solve it.
4. Why is replenishment lead time through the tugger train up to two route cycles?
The card is only picked up on the next round; the material arrives with the round after that.