Value Stream Mapping Metrics and Abbreviations: C/T, C/O, EPEI, L/T

Beginner 6 min read · Updated 2026-10-31

Data boxes and textbooks are full of abbreviations. This glossary lists each metric with its abbreviation, definition, formula and unit, the way the app calculates it. Where German maps (Erlach) use other short forms, they are noted for reference.

Times per process

Performance and quality

Takt, inventory, lead time

Batches, product mix, control

Practice in the editor

Open the steering bracket demo and set the icon set to Rother/Shook: the data boxes then show the abbreviations from this glossary, such as C/T and C/O.

Open the template in the editor Start blank

Free, no sign-up, in your browser. Metrics, timeline and checks are calculated automatically.

Frequently asked questions

What does C/O mean in value stream mapping?

C/O stands for changeover time: the time it takes to switch from one product to the next, measured from the last good part to the first good part.

What is the difference between cycle time and work content?

Cycle time measures the interval between two finished parts. Work content is the work done on the part. If two operators work in parallel, each on one part with 60 s of work content, the cycle time is 30 s. The timeline (processing time) uses cycle time; staffing needs use work content.

Which units are common?

Cycle time and takt time in seconds, changeover time in minutes, days of inventory and lead time in days (hours for short value streams), uptime and scrap rate in percent.

Self-test

1. Which abbreviation stands for changeover time?
C/O = changeover time; C/T is cycle time, P/T is processing time.
2. Which metric is the inverse of the value-added ratio?
Flow factor = lead time ÷ processing time.